September 19th, 2008
Everyone knew the first crossing of the PEAK 2 PEAK Gondola’s Sky Cabins was going to be a momentous occasion. We just didn’t know exactly when it would happen. The Sky Cabins were on the mountain, the carriages were installed and the only thing left to do was wait for the okay from the mechanical and electrical teams.
On Thursday, September 18 a press event was held to announce the official opening date of December 12 as well as to show off the Blackcomb terminal building and all of the Sky Cabins. There were even a few cabins out on the line! To our surprise, Thursday was also the day we found out it was very likely the first twelve cabins would be making their way across the 4.4km/2.73 mile span to Whistler Mountain the very next day on Friday, September 19.
Finally, the day we had all been waiting for (besides the official opening) was here! We were told it would happen after 8am so we made sure to be on the mountain early. Time passed with no action until finally around 10:30am we could make out a faint red blob against Blackcomb’s flank.
My cell phone rang and I was told by Construction Manager Rick Temple that we should watch for the first Sky Cabin and its passenger, Mathias Zundrell. Passenger….WHAT!?
Apparently, it is normal procedure for a Doppelmayr engineer to ride the carriage of the first gondola across, never mind if that puts him 436m/1,427ft above the valley floor with just a harness and a hardhat!
Mathias looked very nonchalant from his perch on Sky Cabin No. 5 and he waved as he glided by high above us. At each lift tower the PEAK 2 PEAK stopped so he could check the gondola’s mechanisms. The remaining Sky Cabins followed and now Whistler’s terminal is housing twelve Sky Cabins so the remaining 16 can be put on the line over at the Blackcomb terminal.
Construction on the terminal buildings is still ongoing but we are getting close to the end of this two year construction project!
September 18th, 2008
As early as 8 a.m. on Friday, September 19, twelve PEAK 2 PEAK Gondola Sky Cabins will make the very first, epic journey across the 4.4km/2.73 mile span between Blackcomb and Whistler Mountains. With the official opening day of December 12, 2008 announced this milestone is all the more exciting.
…Read More 
September 18th, 2008
Whistler Blackcomb’s PEAK 2 PEAK Gondola will officially open to the public December 12, 2008. This engineering marvel is set to become a new Canadian tourism icon, and will forever revolutionize the way visitors experience this four-season resort.
“This spring we had to move massive amounts of snow so it was a slow start but we have been able to stay on track with each construction phase,” says Rick Temple, PEAK 2 PEAK Gondola Construction Manager. “To be at this point in construction at this time is unheard of. Typically for a lift installation you are fighting the weather in November to get things done. However due to the incredible work by everyone involved we are ahead of schedule. We are very excited to have our official opening day announced and are looking forward to the day when our guests can experience this gondola.”
The arrival of 28 Sky Cabins, including two with glass floors, and the completion of the PEAK 2 PEAK Gondola ropework has set the stage for what will be the biggest construction milestone of the lift installation – the first Sky Cabin to cross the record-breaking 3 kilometre/1.88 mile, unsupported span between Whistler and Blackcomb mountains.
Through October and November load testing will take place as well as evacuation training and simulations, and operator training. The PEAK 2 PEAK Gondola will also be examined by the British Columbia Safety Authority through their Passenger Ropeways Safety Program which regulates the safety of lifts.
“There is always a ton of anticipation for the winter season and being able to announce the official opening for the PEAK 2 PEAK Gondola gives our guests something else to look forward to this winter, a definitive date to mark on their calendars,” says Dave Brownlie President and Chief Operating Officer of Whistler Blackcomb. “We know that on December 12, the way our guests use Whistler Blackcomb will be changed forever and we are extremely excited for that day to come.”
September 8th, 2008
The completion of the PEAK 2 PEAK Gondola ropework and the arrival of 28 Sky Cabins set the stage for what will be the biggest construction milestone of the lift installation – the first Sky Cabin to cross the record-breaking 3 kilometre/1.88 mile, unsupported span between Whistler and Blackcomb mountains.
“With the haul rope spliced and all 28 Sky Cabins transported to the Blackcomb terminal, our next objective will be to get the cabins on the line and to send 12 across the span to Whistler,” says Rick Temple, PEAK 2 PEAK Gondola Construction Manager. “We are aiming to send them over by mid to late September, and are on track for the upcoming December grand opening.”
The Sky Cabins were shipped across the Atlantic from Olten, Switzerland where they were manufactured by CWA, global leader in design and construction of cableway vehicles. The Sky Cabins were then loaded onto ten trucks for the journey through Canada. Two cabins feature glass floors, enclosed by a railing, for a bird’s eye view of the Fitzsimmon’s Valley 436 metres/1,430 feet below.
Another significant milestone was the splicing of the haul rope to create a continuous loop, which took place August 29 and 30. The splice was 68 metres/220 feet long, and took a crew of 14 people over 15 hours to complete. Norm Duke, a FATZER AG certified splicer from Wyoming, lead the team of seven Whistler Blackcomb employees and six Doppelmayr/Garaventa employees to complete the job. Duke has spliced many of Whistler Blackcomb’s FATZER AG ropes and spliced the Symphony Express rope in 2006. The splice was achieved by untwining strands from each end of the steel cable and then re-braiding them together to ensure a perfect bind that maintains the haul rope’s diameter of 46mm.
Doppelmayr’s unique 3S gondola technology has each cabin traveling along two 56mm track ropes which bear the weight of the Sky Cabins, with the haul rope pulling in the middle of the two tracks. The haul rope was the only splice needed for the PEAK 2 PEAK Gondola since the track ropes are stationary and do not loop from Blackcomb to Whistler.
The terminal buildings are nearing completion with cladding installation in the final stages and station set-up taking place. Construction progress of the PEAK 2 PEAK Gondola is captured daily via webcams, and weekly via photography and construction blogs on the PEAK 2 PEAK Gondola microsite at www.whistlerblackcomb.com. The PEAK 2 PEAK Gondola will open in December.
September 2nd, 2008
All PEAK 2 PEAK Gondola cables are on line and tensioned with the completion of the haul rope splice taking place August 29 and 30th.
The splice was 68m/220 feet long, and took a crew of 14 people over 15 hours to complete. Norm Duke, a Fatzer AG certified splicer from Wyoming, lead the team of seven Whistler Blackcomb employees and six Doppelmayr/Garaventa employees to complete the job.
It is a “long splice” where strands from each end of the cable are untwined and then re-braided together without the plastic core of the rope to ensure a perfect bind that maintains the haul rope’s diametre of 46mm.